DWH & Bovis Works 27.10.21

October 27, 2021

Dear Residents

Please see the below works updates provided by DWH and Bovis Homes. Any queries that residents have should be referred to the respective developer.

DWH

There will be two road closures across the DWH phases between the following dates, 27/10/21 until 05/11/21, these dates are weather dependent.

The first section of road to be closed is next to 1 Ashlee Crescent, the second exit and the second closure will be by 11 John Ruskin Road, there will be no access into the Crest Nicholson phase and properties though this section of road. The primary works will be so DWH can insert surface water gullies.

DWH & Bovis Works 

This information was shared by the Bovis Technical Team.

There will be works on-going in and around the Bovis Phase at TGV that will impact the DWH Phase, please see the below.

  • Tadpole 2.2 Park View there will be an impact on resident parking and traffic
  • Tadpole 2.3 Larks Rise as per the above, impact on resident parking and traffic

Bovis will be completing tarmac topping on the full section of Blackwell Close. There will also be machines, lorries and other large vehicles driving in and out of High Ground. Bovis will provide future works dates once they have been scheduled in.